MORE Bats have been found at a viaduct where an extensive refurbishment plan is underway.

Cormac Solutions Ltd, which is undertaking the works on behalf of Cornwall Council has confirmed that while undertaking refurbishment works on the viaduct, ecological surveys being undertaken to look after the wellbeing of a resident bat colony within the viaduct has revealed that not only is the colony remaining well and healthy during the works, they’ve been busy breeding.

The news about the bats was revealed in a community update on the ongoing works, which is currently in a second phase that will last until February 2027.

The second phase includes improvements to the cable ducting within the footway to the South Side of the bridge, followed by waterproofing the remaining side of that carriageway.

After completion, there will be a further phase of work undertaken by the owners of trans-atlantic fibre optic communication cables presently within the north footway, with the critical infrastructure moved to the south footway where it will be easier to undertake future maintenance.

There will, later on be a third phase of the works at the viaduct once the relocation of the fibre optic communication cables is complete, see the waterproofing of the north side of the carriageway. The work is scheduled to begin in September 2027.

The scheme will, once completed, protect the 1990s built viaduct, which is used to redirect traffic from Wadebridge for years to come.

Cornwall Council say that this work is necessary to help prevent water ingress that can damage the bridges deck and supporting structures with it ensuring the long term structural integrity and safety of the Camel Viaduct.

A spokesperson for Cormac Solutions Ltd said: “Works at Camel Viaduct are now underway. Since commencement, the team has established the temporary traffic management arrangements and site safety measures have been put in place, with barriers and protective fencing installed to safeguard both the workforce and members of the public.

“The existing carriageway surface layer has been removed, as have the old kerbs, and taken for recycling. Removal of the existing footway and the redundant ducting beneath is now underway.

“As part of the project, ecological surveys have also been carried out. These inspections confirmed that a resident bat colony remains present within the structure and, encouragingly, the population has increased following successful breeding. The project team is continuing to work closely with ecological specialists to ensure the bats remain protected throughout the programme of works.

“Over the coming week, attention will continue to focus on removal and disposal of the footway and ducts. Preparations for the waterproofing itself will also begin, starting with removal of the red sand asphalt layer that protects the existing waterproofing.

Find out about planning applications that affect you by visiting the Public Notice Portal.

“We would like to thank local residents, businesses and road users for their continued patience while these important maintenance works are carried out. Further updates will be provided as the project progresses and full project details can be seen on the Let's Talk Cornwall project page www.letstalk.cornwall.gov.uk/camel-viaduct."